Alert Icon

PROCESS TO LIFT BOIL WATER ADVISORIES IN WALLED LAKE AND NOVI CONTINUES

DAMAGED PIPE SECTION HAS BEEN REPLACED; PROCESS TO LIFT BOIL WATER ADVISORIES IN WALLED LAKE AND NOVI CONTINUES

• Water pressures in Novi and Walled Lake are currently near normal levels
• Boil Water Advisory remains in effect for Novi and Walled Lake
• Process to lift boil water advisories continues
• Installation of new section of steel main has been completed
• Inspection of adjacent main has determined an additional 20-foot section west of the current break site must be replaced
• Both sections of pipe replacement are expected to be completed this week
• The new work will not impact the mid-week target for lifting the boil water advisories

DETROIT – At approximately 4:30 a.m. Saturday, March 7, 2026, the Great Lakes Water Authority (GLWA) discovered a break on a 48-inch water transmission main on 14 Mile Road at Verona, which is between Drake and Farmington Roads in Farmington Hills.

Field Service crews and emergency contractors have completed the installation of the new 20-foot section of steel main. It is anticipated that the installation should be completed by the end of the day on Monday. After an inspection of the main on either side of the current break area, an additional 20-foot section of distressed main 80-feet west of the current break was identified and will be replaced this week.

The process for lifting the boil water advisories in Novi and Walled Lake continues with Novi and Walled Lake conducting flushing of their systems. The first of two required rounds of water quality testing is being taken today. The second round of testing will be taken 24 hours later. If both rounds of testing come back clear, it is anticipated that the boil water advisories could be lifted by mid-week.

The replacement of the additionally identified 20-foot section of main will not impact the proposed mid-week target for lifting the boil water advisories.
The Oakland County Health Division has created a helpful checklist for residents and businesses to use once Novi and Walled Lake emerge from the boil water advisories.

GLWA will share more information as it becomes available.

Capital Improvement Plan

At GLWA the capital replacement strategy that we are striving for is to increase resiliency of water and wastewater systems, adhere to long term planning document recommendations, active solicitation of stakeholder input and to be the best-in-class planning and execution.

GLWA’s Capital Improvement Plan (CIP) supports the continuation of major capital asset investment in programs and projects that will upgrade the Authority’s aging water and wastewater system infrastructure, as well as the overarching Centralized Service infrastructure that supports both systems.  The CIP is a five-year plan which identifies capital projects and programs and their respective financing options. Annually, this plan is updated to reflect changing system needs, priorities and funding opportunities.


Single Resource Download

CIP Map Viewer

Single Resource Download

CIP Public Dashboard


By The Numbers

0
Active or planned CIP projects
0m
Estimated 5-year Water Expenditure
0m
Estimated 5-year Wastewater Expenditure


Board Approved Capital Improvement Plan 2023-2027

Download the Board approved 5-year Capital Improvement Plan (CIP) 2023-2027 for a look at GLWA’s plans for maintaining and improving the regional system.

Board Approved Capital Improvement Plan 2022-2026

Download the Board approved 5-year Capital Improvement Plan (CIP) 2022-2026 for a look at GLWA’s plans for maintaining and improving the regional system.

Board Approved Capital Improvement Plan 2021-2025

Download the Board approved 5-year Capital Improvement Plan (CIP) 2021-2025 for a look at GLWA’s plans for maintaining and improving the regional system.



Contact GLWA

Contact Us

For general information about GLWA's Capital Improvement Plan please contact Dima El-Gamal via email.
M-F | 9am–5pm