GLWA Experiences Break on Leaking 42-inch Water Main in Auburn Hills’ River Woods Park

->At approximately 3:15 a.m. 5/11/2026, crews from GLWA’s emergency contractors cut through the broken pipe

->At approximately 4:00 a.m. the damaged pipe was removed

->After the damaged pipe was removed crews worked to prepare the site for installation of the new pipe by laying a foundation of gravel for support

->Overnight a separate crew as preparing the new pipe segment for placement

->At approximately 11:15 a.m. the replacement pipe segment was craned into the site, and crews are working to complete the installation process, which is targeted to be finished by Monday night

->Next steps then include filling the pipe with water, pressure testing and disinfection.

->GLWA’s three water trucks continue giving water away at three locations throughout the impacted areas

->Residents of Orion Township, the Village of Lake Orion, City of Rochester Hills, Pontiac, and Auburn Hills should still restrict their water use to only what is absolutely necessary for hydration and essential sanitary purposes

READ MORE HERE.

Find all updates regarding the main break here.

La GLWA está experimentando una ruptura en una tubería principal de 42 pulgadas ubicada en River Woods Park, Auburn Hills. Click aquí para mayor información

United States Army Corps of Engineers to Host Public Flood Study Meeting on April 17

The United States Army Corps of Engineers, Detroit District, is hosting a virtual public meeting regarding the ongoing Southeast Michigan Flood Management Study on April 17th from 6-7pm.

To join on Microsoft Teams:

Teams Meeting Link

Meeting ID: 993 355 198 262
Passcode: Wm7zr68i
Dial in by phone: +1(503)207-9433, Conference ID: 823437709#

To learn more about the study, visit: https://www.lrd.usace.army.mil/semifloodstudy/