STATEMENT: Update on Oakland County transmission main work progress October 26, 2017

Although the Great Lakes Water Authority (GLWA) made great progress in the repair of the 48-inch transmission main yesterday with the installation of the new sections of pipe, during pressure testing late last evening a leak was discovered. The repair of this leak has now been completed, and work continues in earnest to restore service to the impacted communities. We anticipate with the main going back in service at some point today, pressures will be restored throughout the impacted area.

Click here to read the full statement.