Freud Sanitary Pump Station
The purpose of the Freud Pump Station Improvements Project is to improve operability, reliability, integrity, and maintainability of the station over the life of the facility. The Freud Pump Station is critical for successful conveyance of dry and wet weather flow from the eastern portion of the regional system.
Primary scope items include rehabilitation of the eight storm pumps and construction of a new sanitary pump station approximately 1.5 blocks east of the existing pump station. The improvements to the existing pump station include replacement of the pump rotating assemblies, line shafts, and concrete pump supports, installing new dewatering pumps with an approximate 10.8 million gallons per day (MGD) capacity, and providing dedicated access to the station wet well to allow for draining, cleaning, inspections, and maintenance.
The proposed project will improve the reliability of the station in both dry and wet weather conditions. It will reduce the risk of system surcharging and combined sewage backups. The Freud Station will improve water quality during storm events by reliably conveying flow to the Conner Creek CSO Facility for treatment prior to discharge into the Detroit River.
Freud Sanitary Pump Station Overview Map
Freud Sanitary Pump Station Landscape Site Plan
Frequently Asked Questions
There is a small window along Freud St between Tennessee St and Algonquin St where the Ashland Relief Sewer and Fox Creek Relief Sewer run in parallel. This window provides GLWA the opportunity to construct one station that can service both sewers rather than needing to construct two separate stations.
We do not currently anticipate the need to acquire any additional properties.
GLWA and its contractors will maximize time each day to accomplish the work as efficiently and safely as possible. Crews are expected to be working from 7:00 AM until 5:00 PM, Monday-Friday.
GLWA’s construction and engineering team will use abatement and dust control techniques, such as misting, when demolition of existing structures occurs. While we are excavating the site for construction, there will be routine dust control measures, such as water trucks and road sweepers, used to control dust on-site and the access roads to and from the site. The contractor will keep the roads clean during all phases of the work.
Residential water services should not be disrupted by the construction.
Freud Sanitary Pump Station FAQs
Click here to read the full Frequently Asked Questions document.
Meetings & Community Events
August 31, 2023 – Flood Mitigation Efforts with DWSD – DOWNLOAD PRESENTATION
February 24, 2024 – Water Resiliency Town Hall – DOWNLOAD PRESENTATION
March 18, 2024 – Community Leader Discussion – DOWNLOAD PRESENTATION
March 19, 2024 – District 4 Meeting – DOWNLOAD PRESENTATION
April 9, 2024 – Community Engagement Event at Immanuel Grace Church – DOWNLOAD PRESENTATION
May 6, 2024 – Public Health and Safety Committee Meeting – DOWNLOAD PRESENTATION
May 20, 2024 – District 4 Meeting – DOWNLOAD PRESENTATION
June 26, 2024 – Community Engagement and Design Review at Eastlake Baptist Church – DOWNLOAD PRESENTATION
July 31, 2024 – Community Engagement Event at Eastlake Baptist Church – DOWNLOAD PRESENTATION
November 21, 2024 – City Planning Commission Public Hearing – DOWNLOAD PRESENTATION
December 11, 2024 – Community Engagement Event at Eastlake Baptist Church, 5:30pm
March 19, 2025 – Community Engagement Event at Eastlake Baptist Church, 5:30pm
May 21, 2025 – Community Engagement Event at Eastlake Baptist Church, 5:30pm
September 17, 2025 – Community Engagement Event at Eastlake Baptist Church, 5:30pm
Additional Project Communications