Alert Icon

GLWA Continues Emergency Response Work on 54-inch Water Main in Southwest Detroit

GLWA CONTINUES EMERGENCY RESPONSE WORK ON 54-INCH WATER TRANSMISSION MAIN IN SOUTHWEST DETROIT

Repairs on GLWA’s 54-inch water transmission main have been completed.
DWSD has completed the repair of its six-inch water main and water quality testing is underway.
DTE Energy is scheduled to repair its gas main the week of March 10.
Sewer cleaning in the impacted area to remove debris created by the break has been completed.
GLWA engineering and operations teams are evaluating the best next steps to ready the 54-inch transmission main for service.

DETROIT – The Great Lakes Water Authority (GLWA) continues its critical role as a part of the broader emergency response to a break on a 54-inch steel water transmission main at Beard and Rowan in Southwest Detroit that occurred in the early morning hours of Monday, February 17, 2025.

GLWA crews and contractors have completed the repair of the 54-inch transmission main. The Detroit Water and Sewerage Department (DWSD) has also completed the repair of its six-inch water main that was damaged in the original main break, and the required water quality testing will be complete by the end of this week. GLWA and DWSD have also completed the cleaning of sewers in the impacted area to remove debris created by the break.

DTE Energy crews are scheduled to complete the repair of its damaged gas line the week of March 10, 2025.
With the repair of the 54-inch main complete, GLWA’s engineering and operations teams are evaluating the full length of the main to determine the best next steps to ready it for service.

More updates will be provided as they become available.

Residents impacted by the water main break can call (313) 774-5261 to be connected to emergency resources through the City of Detroit.

Freud Sanitary Pump Station

The purpose of the Freud Pump Station Improvements Project is to improve operability, reliability, integrity, and maintainability of the station over the life of the facility. The Freud Pump Station is critical for successful conveyance of dry and wet weather flow from the eastern portion of the regional system.

Primary scope items include rehabilitation of the eight storm pumps and construction of a new sanitary pump station approximately 1.5 blocks east of the existing pump station. The improvements to the existing pump station include replacement of the pump rotating assemblies, line shafts, and concrete pump supports, installing new dewatering pumps with an approximate 10.8 million gallons per day (MGD) capacity, and providing dedicated access to the station wet well to allow for draining, cleaning, inspections, and maintenance.

The proposed project will improve the reliability of the station in both dry and wet weather conditions. It will reduce the risk of system surcharging and combined sewage backups. The Freud Station will improve water quality during storm events by reliably conveying flow to the Conner Creek CSO Facility for treatment prior to discharge into the Detroit River.

Single Resource Download

Freud Sanitary Pump Station Overview Map

Single Resource Download

Freud Sanitary Pump Station Landscape Site Plan

Frequently Asked Questions

There is a small window along Freud St between Tennessee St and Algonquin St where the Ashland Relief Sewer and Fox Creek Relief Sewer run in parallel. This window provides GLWA the opportunity to construct one station that can service both sewers rather than needing to construct two separate stations.

We do not currently anticipate the need to acquire any additional properties.

GLWA and its contractors will maximize time each day to accomplish the work as efficiently and safely as possible. Crews are expected to be working from 7:00 AM until 5:00 PM, Monday-Friday.

GLWA’s construction and engineering team will use abatement and dust control techniques, such as misting, when demolition of existing structures occurs. While we are excavating the site for construction, there will be routine dust control measures, such as water trucks and road sweepers, used to control dust on-site and the access roads to and from the site. The contractor will keep the roads clean during all phases of the work.

Residential water services should not be disrupted by the construction.

Freud Sanitary Pump Station FAQs

Click here to read the full Frequently Asked Questions document.

Meetings & Community Events

August 31, 2023 – Flood Mitigation Efforts with DWSD – DOWNLOAD PRESENTATION

February 24, 2024 – Water Resiliency Town Hall – DOWNLOAD PRESENTATION

March 18, 2024 – Community Leader Discussion – DOWNLOAD PRESENTATION

March 19, 2024 – District 4 Meeting – DOWNLOAD PRESENTATION

April 9, 2024 – Community Engagement Event at Immanuel Grace Church – DOWNLOAD PRESENTATION

May 6, 2024 – Public Health and Safety Committee Meeting – DOWNLOAD PRESENTATION

May 20, 2024 – District 4 Meeting – DOWNLOAD PRESENTATION

June 26, 2024 – Community Engagement and Design Review at Eastlake Baptist Church – DOWNLOAD PRESENTATION

July 31, 2024 – Community Engagement Event at Eastlake Baptist Church – DOWNLOAD PRESENTATION

November 21, 2024 – City Planning Commission Public Hearing – DOWNLOAD PRESENTATION

December 11, 2024 – Community Engagement Event at Eastlake Baptist Church – DOWNLOAD PRESENTATION

March 19, 2025 – Community Engagement Event at Eastlake Baptist Church, 5:30pm

May 21, 2025 – Community Engagement Event at Eastlake Baptist Church, 5:30pm

September 17, 2025 – Community Engagement Event at Eastlake Baptist Church, 5:30pm

Contact GLWA

Construction Hotline

Connect with the construction team at Kokosing
Contact GLWA

Contact

Connect with the Freud Sanitary Pump Station Project Manager